The Liberty Bank Building project is approaching some exciting milestones as we move towards the new year. Here are some of the construction activities you can expect to see this coming month:
  • Installation of underground electrical and plumbing;
  • Pouring remaining concrete walls and columns;
  • Pouring concrete slab-on-grade for the north end of the building;
  • Shoring and forming up the Level-2 concrete deck at the north end of the job site;
  • Primary power installation and sidewalk street repair.